Lead times, and what actually delays a shipment
Stock sizes leave our warehouse in 3 to 7 days. Anything made to order is quoted against the mill schedule for that size and grade, and that number is confirmed in writing before you pay a deposit. The rest of the timeline — inspection, booking, transit, customs — is where most delays actually happen.
Stage by stage
| Stage | Typical duration | What starts the clock |
|---|---|---|
| Quotation | 1–2 business days | A complete specification: grade, size, quantity, destination |
| Sample dispatch | Quoted per item | Approval of the sample charge, where one applies |
| Stock sizes | 3–7 days to dispatch | Deposit received and documents in order |
| Made-to-order | Quoted against the mill schedule | Order confirmation, not the enquiry |
| Third-party inspection | Booked to finish before the shipment date | Your instruction to book, or the agency's availability |
| Container booking | Quoted per lane | Dispatch readiness — booking earlier does not help if the goods are not ready |
| Ocean transit, China to US West Coast | Typically 14–25 days depending on port pair | Vessel departure |
| US customs clearance | Days after arrival | Complete and correct entry documents |
We quote dispatch dates, not delivery dates, because we do not control the vessel or the port. Any supplier who promises a door date without a booking is guessing.
What actually causes delay
- An incomplete specification at enquiry — the most common cause, and the easiest to avoid
- A specification change after the deposit, which restarts the production slot
- Inspection booked late, so the report arrives after the vessel has sailed
- Chinese New Year, when the mill and the port slow for two to four weeks
- Customs examination at destination, which is out of both parties' hands
Questions buyers ask about lead time
What is the lead time for stainless pipe from China?
Stock sizes dispatch in 3–7 days. Made-to-order pipe is quoted against the mill schedule for that size and grade, and the date is confirmed in writing with the order.
How fast can you ship stock sizes of 304 sheet?
3–7 days to dispatch. Add ocean transit — typically 14–25 days to a US West Coast port, longer to the Gulf or East Coast.
How much stainless steel do you keep in stock?
200,000 tonnes of standing stock across the product lines, against 500,000 tonnes of annual capacity.
Is 316L seamless pipe stocked or made to order?
Common sizes are stocked; unusual diameters, heavy walls and non-standard lengths are made to order. Ask for the specific size.
How long does 100 tonnes of plate take?
It is quoted against the mill schedule rather than a fixed number, because 100 tonnes is a production run. We confirm the date before the deposit.
What is the fastest way to get steel to the US?
Air freight is possible for samples and urgent small lots and is expensive per kilogram. For production quantities, dispatching from stock and taking the next available vessel is faster than expediting production.
Can you ship part of an order while production continues?
Yes, where the order splits cleanly by size or grade. Partial shipments cost more in freight per tonne but get material to your line sooner.
How long does booking a container take?
It depends on the lane and the season. Booking is only useful once the goods are ready, so we book against dispatch readiness rather than against the enquiry date.
What is the transit time to Houston?
Longer than to the West Coast. We quote an indicative range for your lane rather than a single number, because it varies by carrier and routing.
How long does inspection add?
It is scheduled to finish before the shipment date. Where it slips, the vessel date is the thing at risk — which is why we book it as soon as the production date is firm.
Does Chinese New Year affect delivery?
Yes. The mill and the port slow for two to four weeks around the holiday. Orders placed in December for February delivery should plan for it explicitly.
Can I reserve stock for a later delivery date?
Ask. Reserving stock against a future shipment is possible for repeat buyers, but it is a commercial arrangement rather than a website feature.
What happens if I change the specification after ordering?
The production slot restarts at the change, and the price may move. It is cheaper to spend an extra day on the specification than a week on the change.