Lead times, and what actually delays a shipment

Stock sizes leave our warehouse in 3 to 7 days. Anything made to order is quoted against the mill schedule for that size and grade, and that number is confirmed in writing before you pay a deposit. The rest of the timeline — inspection, booking, transit, customs — is where most delays actually happen.

Stage by stage

StageTypical durationWhat starts the clock
Quotation1–2 business daysA complete specification: grade, size, quantity, destination
Sample dispatchQuoted per itemApproval of the sample charge, where one applies
Stock sizes3–7 days to dispatchDeposit received and documents in order
Made-to-orderQuoted against the mill scheduleOrder confirmation, not the enquiry
Third-party inspectionBooked to finish before the shipment dateYour instruction to book, or the agency's availability
Container bookingQuoted per laneDispatch readiness — booking earlier does not help if the goods are not ready
Ocean transit, China to US West CoastTypically 14–25 days depending on port pairVessel departure
US customs clearanceDays after arrivalComplete and correct entry documents

We quote dispatch dates, not delivery dates, because we do not control the vessel or the port. Any supplier who promises a door date without a booking is guessing.

What actually causes delay

Questions buyers ask about lead time

What is the lead time for stainless pipe from China?

Stock sizes dispatch in 3–7 days. Made-to-order pipe is quoted against the mill schedule for that size and grade, and the date is confirmed in writing with the order.

How fast can you ship stock sizes of 304 sheet?

3–7 days to dispatch. Add ocean transit — typically 14–25 days to a US West Coast port, longer to the Gulf or East Coast.

How much stainless steel do you keep in stock?

200,000 tonnes of standing stock across the product lines, against 500,000 tonnes of annual capacity.

Is 316L seamless pipe stocked or made to order?

Common sizes are stocked; unusual diameters, heavy walls and non-standard lengths are made to order. Ask for the specific size.

How long does 100 tonnes of plate take?

It is quoted against the mill schedule rather than a fixed number, because 100 tonnes is a production run. We confirm the date before the deposit.

What is the fastest way to get steel to the US?

Air freight is possible for samples and urgent small lots and is expensive per kilogram. For production quantities, dispatching from stock and taking the next available vessel is faster than expediting production.

Can you ship part of an order while production continues?

Yes, where the order splits cleanly by size or grade. Partial shipments cost more in freight per tonne but get material to your line sooner.

How long does booking a container take?

It depends on the lane and the season. Booking is only useful once the goods are ready, so we book against dispatch readiness rather than against the enquiry date.

What is the transit time to Houston?

Longer than to the West Coast. We quote an indicative range for your lane rather than a single number, because it varies by carrier and routing.

How long does inspection add?

It is scheduled to finish before the shipment date. Where it slips, the vessel date is the thing at risk — which is why we book it as soon as the production date is firm.

Does Chinese New Year affect delivery?

Yes. The mill and the port slow for two to four weeks around the holiday. Orders placed in December for February delivery should plan for it explicitly.

Can I reserve stock for a later delivery date?

Ask. Reserving stock against a future shipment is possible for repeat buyers, but it is a commercial arrangement rather than a website feature.

What happens if I change the specification after ordering?

The production slot restarts at the change, and the price may move. It is cheaper to spend an extra day on the specification than a week on the change.